Contract Agreement Amount

Rs. 2,98,29,054

Physical Progress

100.00%

Financial Progress

99.45%

Remaining Payment

Rs. 0

Road upgrading and maintenance works Kamalbinayak-Sudal-Adhikari Gaun-Nagarkot (2-9) Road

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 078-79

100.00%

Contract Date: 20-Mar-22

Start Date: 20-Mar-22

Completion Date: 14-Jul-2022 (EOT Not Done)

Project Description

No description available.