Contract Agreement Amount

Rs. 8,51,25,510

Physical Progress

0.00%

Financial Progress

99.41%

Remaining Payment

Rs. 0

Nisti Khola Pul Parlmi Indregauda Jodne

Office: तम्घास सिमल्टारी प्युठान सडक आयोजना, गुल्मी (180)

Fiscal Year: 073-74

0.00%

Contract Date: 14-Dec-17

Start Date: 20-Dec-17

Completion Date: 28-Dec-2020 (EOT Done)

Project Description

No description available.