Contract Agreement Amount

Rs. 1,23,42,500

Physical Progress

100.00%

Financial Progress

99.41%

Remaining Payment

Rs. 0

Rehabilitation Works ( Installation of W-Beam Steel Crash Barrier) on Rapti lokmarga (khaula - Musikot Section)

Office: डिभिजन सडक कार्यालय, चौरजहारी (181)

Fiscal Year: 076-77

100.00%

Contract Date: 17-Jun-20

Start Date: 24-Jun-20

Completion Date: 16-Mar-2021 (EOT Not Done)

Project Description

No description available.