Contract Agreement Amount
Rs. 5,06,900
Physical Progress
0.00%
Financial Progress
99.41%
Remaining Payment
Rs. 0
Gabion works in Sallaghari-Duwakot(F09301),Phuyalgaun- Changunarayan(F09502),Byasi-Changunarayan(F09401)
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 075-76
Contract Date: 13-Jan-19
Start Date: 13-Jan-19
Completion Date: 13-Apr-2019 (EOT Not Done)