Contract Agreement Amount
Rs. 14,88,760
Physical Progress
100.00%
Financial Progress
99.40%
Remaining Payment
Rs. 0
Supply of Construction Materaial at RD Lalitpur ( Pavkage-02)
Office: डिभिजन सडक कार्यालय, ललितपुर (23)
Fiscal Year: 078-79
Contract Date: 26-Jun-22
Start Date: 26-Jun-22
Completion Date: 16-Oct-2022 (EOT Not Done)
Project Description
No description available.