Contract Agreement Amount
Rs. 1,41,83,603
Physical Progress
100.00%
Financial Progress
99.39%
Remaining Payment
Rs. 0
Road improvement works along Dakshin Simawarti Kshetra ko Aadharbhut Bikaslai Prathamiktama Rakhera Dakshin-Uttar Link Purwadhaar Nirman (Bhagwanpur Border-Dhakdahi-Ramnagar-Sikathanchok-Dhekabar-Khaireni Road) Fiscal Year : 2076/77 Project Start Fiscal Year : 2076/77 Project Completion Fiscal Year : 2076/77
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 076-77
Contract Date: 17-Jun-20
Start Date: 17-Jun-20
Completion Date: 09-Jul-2020 (EOT Not Done)
Project Description
No description available.