Contract Agreement Amount

Rs. 3,45,75,616

Physical Progress

100.00%

Financial Progress

99.38%

Remaining Payment

Rs. 0

Periodic Maintenance ( Asphalt concrete ) Works on Araniko highway ( CH 49+600 to CH 59+000) LamidadaDolalghat Road Section

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 076-77

100.00%

Contract Date: 8-Jun-20

Start Date: 8-Jun-20

Completion Date: 26-Oct-2020 (EOT Not Done)

Project Description

No description available.