Contract Agreement Amount
Rs. 26,98,063
Physical Progress
99.94%
Financial Progress
99.37%
Remaining Payment
Rs. 0
Roadway excavation with Retaining Structure and RCC works at Jhigatay Aasrang Borlang Aarughat Sadak Gorkha
Office: डिभिजन सडक कार्यालय, दोलखा (18)
Fiscal Year: 080-81
Contract Date: 9-Nov-23
Start Date: 9-Nov-23
Completion Date: 09-Jul-2024 (EOT Not Done)
Project Description
No description available.