Contract Agreement Amount
Rs. 5,03,74,630
Physical Progress
0.00%
Financial Progress
99.37%
Remaining Payment
Rs. 0
Shree Siddhababa-Ruchi JV Syangaj
Office: उत्तर दक्षिण (कालिगण्डकी करिडोर) लोकमार्ग योजना, पाल्पा (171)
Fiscal Year: 077-78
Contract Date: 23-Mar-21
Start Date: 7-Apr-21
Completion Date: 03-Dec-2022 (EOT Not Done)
Project Description
No description available.