Contract Agreement Amount
Rs. 8,33,300
Physical Progress
100.00%
Financial Progress
99.34%
Remaining Payment
Rs. 0
Recurrent maintenance works in Silgadhi-Chaukhutte Road ,for( drain, Patch repair & shoulder clearing)
Office: सडक डिभिजन, डोटी (35)
Fiscal Year: 076-77
Contract Date: 3-Jun-20
Start Date: 3-Jun-20
Completion Date: 10-Jan-2021 (EOT Done)
Project Description
No description available.