Contract Agreement Amount
Rs. 7,36,33,537
Physical Progress
8.00%
Financial Progress
99.34%
Remaining Payment
Rs. 0
Roadway Protection works along karnali Highway Balighat to Nagma Section (Ch 185+000 to 205+000)Kalikot
Office: हेभिईक्युपमेन्ट डिभिजन, सुनसरी (37)
Fiscal Year: 079-80
Contract Date: 11-Jun-23
Start Date: 11-Jun-23
Completion Date: 24-Aug-2024 (EOT Done)
Project Description
No description available.