Contract Agreement Amount

Rs. 7,36,33,537

Physical Progress

8.00%

Financial Progress

99.34%

Remaining Payment

Rs. 0

Roadway Protection works along karnali Highway Balighat to Nagma Section (Ch 185+000 to 205+000)Kalikot

Office: हेभिईक्युपमेन्ट डिभिजन, सुनसरी (37)

Fiscal Year: 079-80

8.00%

Contract Date: 11-Jun-23

Start Date: 11-Jun-23

Completion Date: 24-Aug-2024 (EOT Done)

Project Description

No description available.