Contract Agreement Amount

Rs. 4,80,43,326

Physical Progress

100.00%

Financial Progress

99.34%

Remaining Payment

Rs. 0

Construction of Pre-Stressed RCC Bridge over Pathara khola Bridge along Gaur-Pipara-Samanpur Road, Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 073-74

100.00%

Contract Date: 14-Nov-17

Start Date: 14-Nov-17

Completion Date: 03-Mar-2022 (EOT Done)

Project Description