Contract Agreement Amount
Rs. 47,17,405
Physical Progress
0.00%
Financial Progress
99.31%
Remaining Payment
Rs. 0
Road Impronement Works on Koputar -Duipipal-Jhyangli Road,Nuwakot
Office: डिभिजन सडक कार्यालय, नुवाकोट (21)
Fiscal Year: 075-76
Contract Date: 5-May-19
Start Date: 5-May-19
Completion Date: 16-Jul-2019 (EOT Not Done)
Project Description
No description available.