Contract Agreement Amount

Rs. 2,14,85,496

Physical Progress

100.00%

Financial Progress

99.31%

Remaining Payment

Rs. 0

एलिट कन्स्ट्रक्सन

Office: उत्तर दक्षिण (कालिगण्डकी करिडोर) लोकमार्ग योजना, पाल्पा (171)

Fiscal Year: 073-74

100.00%

Contract Date: 14-Jul-16

Start Date: 16-Jul-16

Completion Date: 07-Jan-2018 (EOT Not Done)

Project Description

No description available.