Contract Agreement Amount

Rs. 2,26,68,830

Physical Progress

0.00%

Financial Progress

99.30%

Remaining Payment

Rs. 0

Construction of Motorable, Bailey bridge with RCC foundation over Timang Khola in Manang district

Office: डुम्रे बेसीशहर चामे सडक योजना, बेसीशहर लमजुङ (299)

Fiscal Year: 076-77

0.00%

Contract Date: 22-May-17

Start Date: 29-May-17

Completion Date: 10-Dec-2020 (EOT Done)

Project Description

No description available.