Contract Agreement Amount
Rs. 45,65,162
Physical Progress
0.00%
Financial Progress
99.24%
Remaining Payment
Rs. 0
Hariwon Na.Pa.-9 hudai Purwa Paschim Rajmarg dekhi uttar Bishnupur hudai Purano Bajar Abauli Pakargachi hudai Ganesh Chok Tibre Sadak, Sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 075-76
Contract Date: 26-Mar-19
Start Date: 26-Mar-19
Completion Date: 05-Jul-2019 (EOT Not Done)
Project Description
No description available.