Contract Agreement Amount

Rs. 11,32,800

Physical Progress

100.00%

Financial Progress

99.21%

Remaining Payment

Rs. 0

Road widening and upgrading works Hadigaun kalamasi Road

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 077-78

100.00%

Contract Date: 29-Nov-20

Start Date: 29-Nov-20

Completion Date: 13-Mar-2021 (EOT Not Done)

Project Description