Contract Agreement Amount
Rs. 98,65,463
Physical Progress
99.00%
Financial Progress
99.21%
Remaining Payment
Rs. 0
Construction Of Blacktop Road and Retaining Structures along on Hulaki Sadak Dekhi Daschin Katahari Ga.Pa. Aadarsh Nagar hudai Jahada Wada no.3 ko Ram janaki Aadharbhut Bidhyalaya Sadak Morang , Katahari 1 Maheshpur Jamatoko BabiyaBirta sadak Morang and Morang jilla Hativandha-Milanchowk-Nahar Marg-Arun Ittabhatta Harinagra Jahada Ga.Pa., Morang
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 079-80
Contract Date: 6-Dec-22
Start Date: 7-Dec-22
Completion Date: 30-Jun-2023 (EOT Not Done)
Project Description
No description available.