Contract Agreement Amount
Rs. 62,83,323
Physical Progress
100.00%
Financial Progress
99.19%
Remaining Payment
Rs. 0
Construction of Triple Cell RC Box Culvert Works along Mirjapur Chhatauna Bazar Jodne Sadak, Sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 078-79
Contract Date: 27-Dec-21
Start Date: 27-Dec-21
Completion Date: 19-Jun-2022 (EOT Not Done)