Contract Agreement Amount

Rs. 2,30,62,087

Physical Progress

0.00%

Financial Progress

99.18%

Remaining Payment

Rs. 0

Construction of Road Structures, cross drainage works from Mate (74+000) to Myalpokhari (104+000) section along Saljhandi Sandhikharka Dhorpatan Road Project

Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)

Fiscal Year: 074-75

0.00%

Contract Date: 22-Jul-18

Start Date: 22-Jul-18

Completion Date: 29-Apr-2019 (EOT Done)

Project Description

No description available.