Contract Agreement Amount
Rs. 11,88,130
Physical Progress
98.85%
Financial Progress
99.18%
Remaining Payment
Rs. 0
Structure Works in Gokulehswar Dethala Khar Khalanga CH 8+500-13+500 From Khalanaga Side
Office: सुदुरपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय, डोटी (11)
Fiscal Year: 079-80
Contract Date: 8-Nov-22
Start Date: 8-Nov-22
Completion Date: 14-Mar-2023 (EOT Not Done)
Project Description
No description available.