Contract Agreement Amount

Rs. 40,38,967

Physical Progress

100.00%

Financial Progress

99.17%

Remaining Payment

Rs. 0

Blacktop & Structure works on Indraban Samudaya Pipalchautara( Chadani-5) Hudai Devistan Bharatiya Simana Road, Kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 076-77

100.00%

Contract Date: 20-Dec-19

Start Date: 4-Jan-20

Completion Date: 29-Jun-2020 (EOT Not Done)