Contract Agreement Amount
Rs. 31,11,915
Physical Progress
100.00%
Financial Progress
99.15%
Remaining Payment
Rs. 0
M/S Niwas Engineering Consultancy Pvt Ltd,Syangja
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 079-80
Contract Date: 22-Dec-22
Start Date: 22-Dec-22
Completion Date: 30-Jun-2023 (EOT Not Done)
Project Description
No description available.