Contract Agreement Amount

Rs. 4,78,46,387

Physical Progress

100.00%

Financial Progress

99.13%

Remaining Payment

Rs. 0

Road improvement and Structural works on Myanglung Buspark-Tamphula-Sampharjung-Lamebagar-Phedap-Jaljale-poklabang sadak, Tehrathum

Office: डिभिजन सडक कार्यालय, ईलाम (12)

Fiscal Year: 078-79

100.00%

Contract Date: 20-Mar-22

Start Date: 20-Mar-22

Completion Date: 12-Jan-2023 (EOT Done)

Project Description

No description available.