Contract Agreement Amount
Rs. 29,40,510
Physical Progress
100.00%
Financial Progress
99.13%
Remaining Payment
Rs. 0
Road Improvement works along Haripurwa-6 bazar Ishwarpur-15 Soknaha Haripurwa-9 Bagewa Road ,Sarlahi
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 079-80
Contract Date: 31-Jan-23
Start Date: 31-Jan-23
Completion Date: 05-Jul-2023 (EOT Not Done)
Project Description
No description available.