Contract Agreement Amount
Rs. 18,24,690
Physical Progress
98.00%
Financial Progress
99.06%
Remaining Payment
Rs. 0
Road Upgrading Works along Kuirepani-Jhingani-Rampur-Harnok Sworgadwari Road in Pyuthan District.
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 079-80
Contract Date: 12-Jan-23
Start Date: 12-Jan-23
Completion Date: 12-Jan-2024 (EOT Not Done)
Project Description
No description available.