Contract Agreement Amount
Rs. 43,84,650
Physical Progress
100.00%
Financial Progress
99.03%
Remaining Payment
Rs. 0
Balara Chhatauna Sudama Khairwa Chotaul Sisaut Sadak, (Bhagwanpur tole dekhi Balara Bajar Sadak), Sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 076-77
Contract Date: 23-Jan-20
Start Date: 23-Jan-20
Completion Date: 04-Jul-2020 (EOT Not Done)
Project Description
No description available.