Contract Agreement Amount

Rs. 2,58,69,257

Physical Progress

98.27%

Financial Progress

99.02%

Remaining Payment

Rs. 0

Recurrent Maintenace work along Mawa to Itahari section of Mahendra Rajmarga, Aambari to Urlabari section of Bardanga Aambari Urlabari Road, MRM Itahari to Koshi Barrage section, KRM Itahari to Bhedrtar section, Duhabi to Inaruwa Road

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 077-78

98.27%

Contract Date: 2-Mar-21

Start Date: 2-Mar-21

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.