Contract Agreement Amount

Rs. 19,59,031

Physical Progress

0.00%

Financial Progress

99.00%

Remaining Payment

Rs. 1

Roadway Infrastructure Development Works on Sahidpark Kalika Road, Rasuwa

Office: डिभिजन सडक कार्यालय, नुवाकोट (21)

Fiscal Year: 076-77

0.00%

Contract Date: 22-Nov-19

Start Date: 22-Nov-19

Completion Date: 19-Apr-2020 (EOT Not Done)

Project Description

No description available.