Contract Agreement Amount
Rs. 1,03,76,621
Physical Progress
0.00%
Financial Progress
99.00%
Remaining Payment
Rs. 1
Road Construction works on Kalaiya Na.Pa. 17 Bramhapuri Matiyariya Red Cross Tole Road, Bara
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 076-77
Contract Date: 14-Jun-20
Start Date: 14-Jun-20
Completion Date: 15-Jul-2020 (EOT Not Done)
Project Description
No description available.