Contract Agreement Amount
Rs. 16,61,364
Physical Progress
0.00%
Financial Progress
98.99%
Remaining Payment
Rs. 1
Supply of CRM Sub-base Materils, Crushed Chip (13.2mm to 0.09mm) Materials, Semi-Grouting aggregates (37.5 mm to 13.2 mm), Stone Dust, Bitumen Emulsion m/s 65%(Medium Setting) as per Direction of Engineer at Instructed Camp of Road Division Biratnagar
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 078-79
Contract Date: 5-Jul-22
Start Date: 5-Jul-22
Completion Date: 14-Jul-2022 (EOT Done)