Contract Agreement Amount
Rs. 93,55,124
Physical Progress
0.00%
Financial Progress
98.97%
Remaining Payment
Rs. 1
Construction of Road structure, Cross drainage and earthwork in Phalleghar to Dhorpatan(Ch.190+000-196+000)
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 076-77
Contract Date: 2-Jun-20
Start Date: 2-Jun-20
Completion Date: 31-Dec-2020 (EOT Done)
Project Description
No description available.