Contract Agreement Amount
Rs. 68,51,275
Physical Progress
100.00%
Financial Progress
98.96%
Remaining Payment
Rs. 1
Road Improvement works along Parsa dekhi Pipara hudai Chaulikha Raitarkhor hudai main Rajmarg Samma Sadak, Sarlahi
Office: डिभिजन सडक कार्यालय, नुवाकोट (21)
Fiscal Year: 079-80
Contract Date: 6-Feb-23
Start Date: 6-Feb-23
Completion Date: 10-Jul-2023 (EOT Not Done)
Project Description
No description available.