Contract Agreement Amount
Rs. 73,67,827
Physical Progress
68.00%
Financial Progress
98.85%
Remaining Payment
Rs. 1
Maintenance Work of Road (Slide Clearence) in Ch: 23+000 (Dhungre Khola) to Ch: 34+600 (Nigali Deurali) Arghakhachi section along Saljhandi -Sandhikharka - Dhorpatan Road (NH-52)
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 077-78
Contract Date: 30-Apr-21
Start Date: 30-Apr-21
Completion Date: 25-Jan-2022 (EOT Done)
Project Description
No description available.