Contract Agreement Amount
Rs. 15,69,55,272
Physical Progress
0.00%
Financial Progress
98.84%
Remaining Payment
Rs. 1
Construction of RCC Bridges at Thado (72+500) & Wang Khola (75+300)
Office: उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा (57)
Fiscal Year: 074-75
Contract Date: 21-Sep-18
Start Date: 21-Sep-18
Completion Date: 13-Apr-2022 (EOT Done)