Contract Agreement Amount

Rs. 15,38,140

Physical Progress

98.82%

Financial Progress

98.82%

Remaining Payment

Rs. 1

Supply of Crushed Chips (13.2 mm to 0.09 mm) material, semi-grouting aggregates (37.5 mm to 13.2 mm), Stone dust, Bitumen Emulsion M/S 65% (Medium Setting) as Per direction of Engineer at instructed Camp Of Road Division Biratnagar

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 079-80

98.82%

Contract Date: 12-Sep-22

Start Date: 13-Sep-22

Completion Date: 25-Oct-2022 (EOT Not Done)

Project Description

No description available.