Contract Agreement Amount
Rs. 3,83,400
Physical Progress
100.00%
Financial Progress
98.81%
Remaining Payment
Rs. 1
Specific Maintenance Works in Phuyalgaun Changunarayan Road
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 075-76
Contract Date: 16-Apr-19
Start Date: 16-Apr-19
Completion Date: 17-Jun-2019 (EOT Not Done)
Project Description
No description available.