Contract Agreement Amount

Rs. 4,03,41,290

Physical Progress

100.00%

Financial Progress

98.80%

Remaining Payment

Rs. 1

Construction of Pre-Stress RCC Girder bridge Over khullakhet khola.

Office: सडक डिभिजन, डोटी (35)

Fiscal Year: 071-72

100.00%

Contract Date: 10-Sep-15

Start Date: 9-Sep-18

Completion Date: 24-Jul-2018 (EOT Done)

Project Description

No description available.