Contract Agreement Amount
Rs. 32,33,925
Physical Progress
0.00%
Financial Progress
98.78%
Remaining Payment
Rs. 1
Road Safety Works at Dhulikhel-Nepalthok Road Section of Dhulikhel-Sindhuli Bardibas Road
Office: सूर्यविनायक-धुलिखेल, धुलिखेल-सिन्धुली-बर्दिवास सडक आयोजना, काठमाण्डौ (225)
Fiscal Year: 076-77
Contract Date: 26-Nov-19
Start Date: 10-Dec-19
Completion Date: 24-Jun-2020 (EOT Not Done)
Project Description
No description available.