Contract Agreement Amount

Rs. 92,65,416

Physical Progress

100.00%

Financial Progress

98.77%

Remaining Payment

Rs. 1

Improvement of Tallo Garjamini -Asaina- Sikalpatti - Thada- Janapuri -Dhakaniya- Ranipur- Basantapur- Bansaha - Ganeshpur -Deepnagar -Amarpur- Naukhari -Manikapur dham Road, Kanchanpur (Chainage-1+800 to 3+325)

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 076-77

100.00%

Contract Date: 23-Jun-20

Start Date: 30-Jun-20

Completion Date: 28-Mar-2021 (EOT Not Done)

Project Description

No description available.