Contract Agreement Amount

Rs. 32,15,394

Physical Progress

98.77%

Financial Progress

98.77%

Remaining Payment

Rs. 1

Roadway Excavation, Gabion wall and cross drainage work at Suchidada-Juni Road, Dailekh

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

98.77%

Contract Date: 8-May-20

Start Date: 8-May-20

Completion Date: 13-Jul-2020 (EOT Not Done)

Project Description

No description available.