Contract Agreement Amount
Rs. 3,32,08,747
Physical Progress
100.00%
Financial Progress
98.73%
Remaining Payment
Rs. 1
Road Upgrading works at Bhaktapur Army Camp Nagarkot
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 078-79
Contract Date: 15-Jul-22
Start Date: 15-Jul-22
Completion Date: 10-May-2023 (EOT Not Done)
Project Description
No description available.