Contract Agreement Amount

Rs. 93,14,20,278

Physical Progress

100.00%

Financial Progress

98.69%

Remaining Payment

Rs. 1

Design and Build of 1. Rapti Bridge Connecting Sisniya VDC-2 & Gobadiya VDC-6

Office: पुल योजना, पश्चिम क्षेत्र सेक्टर नं. ३, वांके (190)

Fiscal Year: 072-73

100.00%

Contract Date: 12-Jul-16

Start Date: 12-Jul-16

Completion Date: 11-Oct-2021 (EOT Done)

Project Description

No description available.