Contract Agreement Amount
Rs. 3,98,86,108
Physical Progress
98.65%
Financial Progress
98.65%
Remaining Payment
Rs. 1
Rehabilitation Work on Surkhet-Jumla Road, Dailekh (CH: 45+000-132+000)
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 074-75
Contract Date: 1-Jun-18
Start Date: 1-Jun-18
Completion Date: 03-Apr-2019 (EOT Done)
Project Description
No description available.