Contract Agreement Amount

Rs. 19,90,43,021

Physical Progress

100.00%

Financial Progress

98.64%

Remaining Payment

Rs. 1

upgrading of manmat kalaya matiwarwa roaad 2072/73/016

Office: हुलाकी राजमार्ग निर्देशनालय​, काठमाण्डौ (230)

Fiscal Year: 072-73

100.00%

Contract Date: 19-Oct-16

Start Date: 2-Nov-16

Completion Date: 31-Dec-2020 (EOT Done)

Project Description

No description available.