Contract Agreement Amount
Rs. 19,90,43,021
Physical Progress
100.00%
Financial Progress
98.64%
Remaining Payment
Rs. 1
upgrading of manmat kalaya matiwarwa roaad 2072/73/016
Office: हुलाकी राजमार्ग निर्देशनालय, काठमाण्डौ (230)
Fiscal Year: 072-73
Contract Date: 19-Oct-16
Start Date: 2-Nov-16
Completion Date: 31-Dec-2020 (EOT Done)
Project Description
No description available.