Contract Agreement Amount
Rs. 29,90,30,603
Physical Progress
100.00%
Financial Progress
98.63%
Remaining Payment
Rs. 1
yedukuwa mahinathpur roadUR012
Office: हुलाकी राजमार्ग निर्देशनालय, काठमाण्डौ (230)
Fiscal Year: 072-73
Contract Date: 18-Oct-16
Start Date: 1-Nov-16
Completion Date: 16-Jul-2020 (EOT Done)
Project Description
No description available.