Contract Agreement Amount

Rs. 61,25,001

Physical Progress

75.00%

Financial Progress

98.59%

Remaining Payment

Rs. 1

Construction of Slab Culvert at Kohabara Sanischare Baalubathan Maharranijhoda Gauradaha Baigundhura Shivagunj Road, Jhapa

Office: डिभिजन सडक कार्यालय, झापा (13)

Fiscal Year: 076-77

75.00%

Contract Date: 24-Nov-19

Start Date: 24-Nov-19

Completion Date: 13-May-2020 (EOT Not Done)

Project Description

No description available.