Contract Agreement Amount

Rs. 19,97,385

Physical Progress

0.00%

Financial Progress

98.58%

Remaining Payment

Rs. 1

Construction of Causeway Works on Santpur Bishrampur Haraiya Binagra Madhopur Pipara Bajar hudai Gaur Sadak, Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 077-78

0.00%

Contract Date: 21-Sep-20

Start Date: 27-Sep-20

Completion Date: 19-Dec-2020 (EOT Not Done)

Project Description

No description available.