Contract Agreement Amount
Rs. 81,93,100
Physical Progress
0.00%
Financial Progress
98.54%
Remaining Payment
Rs. 1
Roadway Excavation, Gabion and Stone Soling Work Along Udayapurko Mainamaini Wasepla Bhojpurko Hasanpur Ghodetar Bhojpur Sadarmukam Hudai Sankhuwasabha Jodne Sadak (Dingla- Satighat Section)
Office: डिभिजन सडक कार्यालय, तुम्लीङटार, संखुवासभा (174)
Fiscal Year: 076-77
Contract Date: 20-Sep-20
Start Date: 20-Sep-20
Completion Date: 13-Apr-2021 (EOT Not Done)