Contract Agreement Amount

Rs. 81,93,100

Physical Progress

0.00%

Financial Progress

98.54%

Remaining Payment

Rs. 1

Roadway Excavation, Gabion and Stone Soling Work Along Udayapurko Mainamaini Wasepla Bhojpurko Hasanpur Ghodetar Bhojpur Sadarmukam Hudai Sankhuwasabha Jodne Sadak (Dingla- Satighat Section)

Office: डिभिजन सडक कार्यालय, तुम्लीङटार, संखुवासभा (174)

Fiscal Year: 076-77

0.00%

Contract Date: 20-Sep-20

Start Date: 20-Sep-20

Completion Date: 13-Apr-2021 (EOT Not Done)

Project Description

No description available.