Contract Agreement Amount

Rs. 23,59,117

Physical Progress

100.00%

Financial Progress

98.54%

Remaining Payment

Rs. 1

Kothi-Dhankhola Section, Kapilvastu.

Office: सडक डिभिजन, कपिलवस्तु (29)

Fiscal Year: 079-80

100.00%

Contract Date: 28-Aug-22

Start Date: 5-Sep-22

Completion Date: 28-Nov-2022 (EOT Not Done)

Project Description

No description available.